Quality, Service & Commitment

INTERRA NEWS

  • 26 Oct 2017

    INTERRA To Host Ribbon Cutting With Bolingbrook Mayor Celebrating Going Green

  • 21 Jul 2017

    Recipient Of Service Award Thanks INTERRA for Engineering Support With Jane Byrne Circle Interchange

  • 15 Mar 2017

    INTERRA, Inc. Full-Time Field Technician Openings in Franklin, WI

More News

Certified

Laboratory Certifications

  • IL & WI State DOTs
  • ASTM
  • AASHTO
  • USACE

 

Firm Certifications

  • DBE with IDOT
  • MBE with City of Chicago

Read More

Testimonials

LPV111, New Orleans East Back Levee, Louisiana: “Management was attentive to our needs, provided the advice needed to make cost effective decisions, and followed through with action in the field.  This was a very high profile project with a one …

Read More

Chalmette Loop Levee (LPV146) – Army Corps of Engineers

INTERRA Services

  All materials testing from INTERRA accredited on-site laboratory

  Proctors, Atterberg Limits, Grain Size/Hydrometer, Percent Fines, Organic Content, Moisture Content (Oven/Microwave) completed on approximately 330 soil samples

  Casting/Compressive Strength tests completed on over 11,000 concrete cylinders

  Field Compaction Tests using Nuclear Density Gauge and Sand Cone Tests

  100% Visual Testing (VT) and 25% Magnetic Particle Testing (MT) of approximately 15,000 Fillet Welds in the field

  100% Visual Testing and 25% Ultrasonic Testing (UT) of Butt Joints on approximately 750 H-Piles in the field

Project Summary

Saint Bernard Levee Partners was tasked by the USACE to construct the approximately 8-mile long concrete T-wall levee from Bayou Dupre to Hwy 46 in Saint Bernard, LA.  INTERRA provided complete construction materials testing and inspection for soils, concrete, asphalt and steel.  To accomplish this high-profile, fast-tracked project within the necessarily aggressive schedule, INTERRA established an on-site laboratory and had it successfully accredited by the USACE in matter of weeks.  The on-site laboratory not only maintained required quality standards over the course of the project, but was able to accurately process and document a dramatically large number of widely varied tests.